The engineering, procurement, and construction (EPC) industry is entering another strategic reset as legacy projects that were bid under outdated risk models continue to squeeze margins, strain cash, and fuel investor concerns globally.
The warning signs are hard to ignore. One publicly traded global engineering and infrastructure company recorded a more than $300 million pre-tax charge recently on a single legacy construction management project awarded in 2019. Bid under terms the company says it wouldn’t accept today, the project has faced subcontractor productivity issues, schedule delays, and continued cash outflows.
Another US-based global EPC contractor is working through a legacy “loss project backlog,” with charges tied to infrastructure, mining, and ongoing litigation. Other large global engineering and construction companies also report impairments and overruns, leading them to reject high-risk contracting models. We’ve seen this before. Today’s cycle echoes the 2017–19 fixed-price crisis, when large, lump-sum turnkey (LSTK) projects shifted from valuable backlogs to costly earnings liabilities, forcing many EPC companies to tighten bid discipline and shift toward more-predictable, lower-risk services.
The difference now is the operating environment. EPC risk is amplified by labor scarcity, supply-chain fragmentation, tariff and trade-policy volatility, inflation, and subcontractor stress on top of perennial challenges like design maturity, emerging technologies, and aggressive delivery schedules.
The industry isn’t witnessing the death of LSTK. Fixed-price models can have a place where design is mature, quantities are reliable, technology is proven, labor is available, and risk is priced confidently.
Fixed-price contracts can become a liability when project assumptions outpace the cost, schedule, productivity, and risk assumptions underpinning the bid. Tariffs are just one example of unpredictable factors that can widen the cost gap and increase risk. A bid priced against one set of import duties on steel, aluminum, or specialized equipment can be invalidated by a policy change long before the project reaches substantial completion. And unlike inflation, which moves gradually, tariff changes can shift overnight and target specific countries or sectors. A fixed-price contract that doesn’t explicitly address tariff exposure is effectively betting the current trade environment holds for the life of the project.
In response, many contractors now focus on commercial discipline, moving away from lump-sum contracts and embracing collaborative and shared-risk structures. Under alternatives like EPCM (engineering, procurement and construction management), reimbursable, or progressive design-build contracts, the contractor manages delivery while the owner assumes a greater share of risk. They’ve also invested in ERP software to tighten project controls and better track labor, materials, and risk.
Although these smarter contracts and ERP tools are essential, they may not be enough. Losses from material shortages, delays, and indirect costs often take shape and begin to erode margins before they appear in ERP systems. Resilience requires a connected digital operating model that links the bid room, engineering, procurement, project controls, commercial teams, and field execution. Modern tools like sensors, drones, and site imagery can help surface risks sooner and trigger action.
The next EPC winners won’t just aim to avoid fixed price contracts. They’ll likely see risks earlier, manage them smarter, and remediate before operational issues become financial losses.
The circumstances may differ, but the pressures are familiar—fixed-price risk, weak front-end definition, schedule delays, productivity shortfalls, procurement stress, and subcontractor or partner performance. Once a project is underway, the ability to recover costs can be limited, turning project challenges into margin and cash pressure. Across the global EPC market, just a handful of underperforming projects can materially impact earnings, cash flow, and investor confidence.
| Contractor profile | Reported loss / impairment | Strategic signal |
| US-based global EPC and engineering contractor | Multiple charges; loss project backlog | Continued runoff of legacy risk across infrastructure, mining, and litigation |
| South Korean EPC contractor | ~ ₩337B / $250M+ | Project impairments linked to execution, cost, and schedule exposure |
| South Korean engineering and construction contractor | ₩1.77T in 4Q24 | Overseas project cost overruns, one-off charges |
| European energy and infrastructure contractor | ~€132M EBITDA | Waste-to-energy project delays and cost overruns |
| Global engineering and consulting firm | ~$955M including goodwill and EPC-related charges | Strategic exit from large-scale EPC/LSTK contracting |
| US-based specialty infrastructure and E&C contractor | ~$35M–$40M | Renewable project overruns |
| Japanese-based global EPC contractor | ¥14.5B engineering segment loss; ¥35.7B construction-loss provisions | Overseas EPC cost growth and risk-response expenses; schedule, labor, subcontractor, and execution pressures |
| Japanese global LNG / process EPC contractor | ¥15.0B operating loss; ¥15.8B net loss | Major US LNG project exposure; JV-partner, completion-cost, and execution pressures |
Source: Publicly reported EPC / E&C losses 2022-2026
The industry isn’t witnessing the death of LSTK. Fixed-price models can have a place where design is mature, quantities are reliable, technology is proven, labor is available, and risk is priced confidently.
What’s increasingly being challenged is the casual transfer of poorly defined risk.
The market is turning to more collaborative, phased models to help delay risk transfer until the project is mature enough to price it. They extend from EPCM and early contractor involvement to target-price contracts, open-book estimating, and phased conversion to lump sum.
For owners, this means recognizing that the lowest upfront price may not deliver the best outcome. Execution certainty is more valuable than nominal cost certainty.
For contractors, this means asking a different question. Instead of “Can we win it?” the focus is now on, “Can we deliver it at the margin we’re underwriting with risks we can actually control?”
Commercial discipline is essential, but even with stronger bid reviews, contract governance, and thorough ERP reporting, many EPC firms see project decline too late to change outcome.
That makes a connected, technology-powered EPC operating model essential.
This next-generation model goes beyond ERP and helps connect the digital core to the field edge, linking estimating, schedule, cost, procurement, risk, and forecasting with real-time signals on labor, materials, progress, and productivity. The goal is to use better data to drive earlier decisions on whether to bid, how to price risk, when to lock in commercial terms, when to intervene, and when to secure recovery rights.
Integrating systems is the key to closing the certainty gap. Field productivity should flow into the forecast, the impact of procurement delays on scheduling and commercial results should be clear, design maturity should inform fixed-price readiness, and subcontractor delays should initiate recovery plans and commercial notices.
Use the current loss cycle as a catalyst to modernize your commercial and operating models and build risk intelligence into project selection, pricing, and delivery. The priorities are clear. Strengthen front-end risk discipline, connect estimation to execution, extend visibility to the field, build predictive project controls, and close the learning loop. Taking these actions can help you price risk more deliberately, identify margin pressure earlier, and apply lessons to future bids.
| Priority | What it means | Why it matters |
| Strengthen front-end discipline | Use risk-adjusted return, design maturity, and capacity checks before bidding | Helps prevent underpriced risk from entering backlog |
| Connect estimate to execution | Make bid assumptions traceable into schedule, cost, and forecast systems | Reveals when the project being built differs from the project that was priced |
| Digitize the field edge | Capture labor, quantities, constraints, and materials readiness in real time | Improves productivity and helps reduce lost time |
| Build predictive controls | Use leading indicators to identify margin-at-risk early | Enables intervention before losses are embedded |
| Digitize commercial management | Connect contract rights, notices, and change documentation to project events | Helps improve recovery and protect entitlement |
| Close the learning loop | Feed actual project performance back into estimating and bid governance | Helps apply the learnings from each project to improve the next bid |
For owners, the question is shifting from “Who will accept the lowest fixed price?” to “What risk allocation gives this project better chance of success?”
Seeking fixed-price certainty before scope, design, and execution plans are mature can yield a price without any certainty of delivery, raising the risk of claims, delays, and cost overrun. Stronger front-end definition, earlier contractor involvement, and commercial models that allocate risk to the party better able to manage it can improve outcomes.
Tariff risk, especially, deserves the same explicit allocation as other unpriceable risks. Owners who leave tariff exposure ambiguous in the contract are effectively asking contractors to price in a hedge against future trade policy, which can either inflate the bid or get absorbed silently until it resurfaces as a claim.
For contractors, the challenge is often discipline. Strong demand can make backlog growth attractive, but not all backlogs create equal value.
Leading contractors will likely be more selective and pursue work where they have an execution advantage, reliable labor and supply chains, and commercial terms that reflect the risks they’re taking. The test is to understand and control the risk, and to be paid appropriately to take it. If those parameters aren’t met, it may be more effective to restructure the deal or walk away.